EXPANSION AND INCREASING THE CAPACITY OF THE WAREHOUSE COMPLEX IN KYIV REGION

In 2007, in the industrial area of the village Dudarkiv, which is located in Boryspil district of Kyiv region, started the project of a warehouse complex, which included the gradual construction of 14 autonomous blocks and the provision of appropriate infrastructure. However, even at the initial stages of the project investors decided to change the […]

Автор Марія

"

Read more

In 2007, in the industrial area of the village Dudarkiv, which is located in Boryspil district of Kyiv region, started the project of a warehouse complex, which included the gradual construction of 14 autonomous blocks and the provision of appropriate infrastructure. However, even at the initial stages of the project investors decided to change the further concept, including through the financial crisis in 2008. Nevertheless, the active development of the logistics sector in recent years contributed to the resumption of construction of the warehouse complex. Since then the team of the KOMFORTBUD Design Institute joined the work on this object.

 During this time, closely cooperating with the Czech engineering company “RECOC” our employees have performed a significant amount of design work, both in terms of expansion and increasing the capacity of existing facilities, as well as in terms of building new units. Currently we are working on a reconstruction project of the complex with the addition of three separate storage blocks, administrative and household building, a transition gallery and a canteen.

An important part of the design is a multifunctional three-story administrative and household building. There will be offices where the administrative staff will work. There will also be locker rooms, toilets and a canteen. In the project which includes a full complex of all the necessary technological rooms: cold and hot shops, refrigerating and freezing chambers, store rooms for foods, a dining hall for 150 seats.

The construction of the 7th and 8th warehouse blocks according to the project of our specialists is already in progress. The frame of prefabricated reinforced concrete became a constructive basis for the building, partitions were made of sandwich panels. Rectangular storage blocks will have maximally optimized space for storage of products. In addition, they will be equipped with charging stations and a utility room. The premises will be equipped with a fire safety system to create a safe working environment. 

The administration and household complex will be connected with the storage blocks through the transition aboveground gallery, which will be built with metal trusses, and it will be placed on reinforced concrete columns. The start of work with its construction is planned for the near future.

Institute of Design “COMFORTBUD” continues to work actively on the project and performs supervision of the implementation of construction works.